Monday, July 5, 2010
My Happy Ending
Detailing and optimizing
An example of detailing for Box Truss 1
Sunday, June 27, 2010
A different approach
= 17.896kN
Loads were assigned to the 3 dimension model of Main Truss A
Loads assigned to the 3 dimension model of UTAR Grand Hall
The model of UTAR Grand Hall was completed
The completed model of UTAR Grand Hall
Saturday, June 26, 2010
I am one step closer to the completed model
All box trusses were completed
The cover page of meeting minute
Soil Investigation
A sample of borehole log
Main truss and tie truss tied a perfect knot
The formation of box truss was analysed. After that, we found that the formation of Box Truss 1 differs from Box Truss 3. In terms of diagonal member. Box Truss 1 made up of bottom chord(BC), top chord(TC), horizontal member(H), vertical member(V) and diagonal member(D). The model of Box Truss 1 was completed today. Just like before, Box Truss 3 and Box Truss 5 made up of bottom chord(BC), top chord(TC), horizontal member(H), vertical member(V) and diagonal member(D). Box Truss 3 and Box Truss 5 was completed by today.
The tie truss was combined with main truss
Box Truss 1 was modeled
The tie truss
The drawing of tie truss was overlapped on main truss, it was found that tie truss has larger section.
The first step
As for today, the model of Main Truss A, Main Truss B and Main Truss C was completed.
The coordinate of Main Truss A
Friday, June 18, 2010
Grand hall comes grand effort
The latest architect drawings with insufficient information and the passed yet incomplete model and analysis did by Mr. Lim was provided. Part of the project was delegated to Mr. Hameen one of the recently employed trainee from University Malaya. he will be modeling and designing the tie truss. Hence I will be modeling and designing the main truss.
As for today, I studied the drawings and passed analysis provided. After that, proper planing of the project takes place in order to reduce potential mistakes.
The plan view of UTAR grand hall
The cross section view of UTAR grand hall
Thursday, June 3, 2010
The mansion
Main beam: Dead load = 18.55kN/m^2, Live load = 1.5kN/m^2
Secondary beam: Dead load = 4kN/m^2, Live load = 1.5kN/m^2
Wall: Dead load = 8kN/m
The second story was assigned with only uniform distributed roof load. Deflection was adequate. Lateral torsional buckling and plane flexural buckling was adequate as well.
An overview of Hajeedar bungalow's steel truss
The assigned dead load and live load
The deflected shape of Hajeedar bungalow's steel truss
Architects rule the game
After conducting the analysis based on verandah method, it was found that the section used was too huge. Therefore, the diagonal members were retained with the introduction of horizontal member to strengthen the pedestrian bridge.
Additional horizontal member was assigned with the absence of diagonal member
Wednesday, June 2, 2010
A brand new approach
The 3D view and plan view of Pangkor Chalet
The deflected shape of Pangkor Chalet
Tuesday, June 1, 2010
Pile cap design 2P400 and 7P300
An example of pilecap
Sunday, May 16, 2010
The trouble goes on and on...
-I-beam was assigned to the trusses that supports the metal roof that is on both sides of the main roof.
An overview of UNIMAS roof truss
The plane view of UNIMAS roof truss
loads were assigned to the roof truss
The deflected shape of the roof truss
Wrong assumptions
First attempt was made to model the bridge based on the coordinate obtained from the autocad drawings provided. Sadly, it yields an irregular shape. Without much hesitation help was seeked from Mr. Lim. he advised me to make things simpler by rounding up the numbers and use cos-sin-tan method to obtain the coordinate. The corrections and analysis was completed on the day.
The end is futher than I thought
The main truss was changed to triangular shape
Wednesday, May 12, 2010
Pedestrian bridge
The next day, the model of the pedestrian bridge 2 was constructed based on the coordinate obtained. Through my disappoinment, the bridge does not appear to be straight. Help was seek from Mdm. Tan, one of the reputable draughtsman in the consultant firm. I was advised by her to model the bridge as if it is straight, instead of tilted. The model of the bridge was completed on the day.
The analysis continues, dead load assigned is 2kN/m, while live load assigned is 4kN/m. The beam section assigned for top-chord and bottom chord of the bridge is SHS 150x150x8.0. On the other hand, the middle chord made up of SHS 150x150x8.0 and CHS 76x5.0. As for the column, beam section of CHS 324x6.0 was assigned. The supports at column resist translational and rotational movement. While, supports that is located at the end span of the bridge only resists vertical load to allowed expansion and compression of the steel bridge due to influences of heat.
The deflected shape of the bridge
Analysis completed
An overview of UNIMAS roof truss
The deflected shape of UNIMAS roof truss
Super structures
The main truss
The fascia truss - The fascia truss and main truss may looks alike but they are different in terms of loads that acts on it
The tie truss that attaches to main truss - tie truss resists lateral stress
Wednesday, May 5, 2010
Rare opportunity
First, I was advised to design the slab, then proceed to beam and finally the column. Besides that, I was also advised to design by manual calculation before proceed to computer aided design. The purpose of manual calculation is to determine the slab thickness, area of steel bars and numbers of steel bars provided. I was assigned to calculate slab A, slab B and slab C at various location.
Slab A was completed on the day itself. Characteristics of the slab as follows:
-Selfweight of slab = 3.6kN/m^2
-Dead load = 2.5kN/m^2
-Live load = 5.0kN/m^2
-Two way slab
-Slab thickness = 150mm
-Nominal cover = 30mm
-High tensile Steel bar diameter = 10mm
-Support X and span X = 6T10-150mm and 5T10-190mm
-Support Y and span Y = 3T10-320mm and 3T10-320mm
-Deflection is satisfactory for span X and span Y
Disaster strikes
Section properties
The section properties of service lift A at ground level
Thursday, April 22, 2010
Defy convention
First of all, I did checking for the tender rate and tender amount provided by the invited tenderer. After that, A set of data which regards comparison of BQ - Bills (Based on 6 weeks completion peroid) and comparison of BQ - work, rate and comunt (Based on 6 weeks completion period) was tabulated by using Microsoft Excel. Then the soil investigation tender report which consists of introduction, calling and closing of quotations, validity of quotations, quotation results, tenders shorlisted for analysis, arithmetical checks, comparison of quantities, comments, conclusion and recomendation was wrote.
The completed soil investigation tender report was submitted to Mr. Siva for checking. After a comprehensive check on the tender report was carried out by my supervisor. A few amendments were required for compariosn of BQ - Bills, comments, conclusion and recomendations. Finally, the corrected tender report was then submitted to Mr. Siva.
Monday, April 19, 2010
Having doubts?
After conducting the analysis. It yields a results that comes very close to the solution provided by example 11 as in the book. In conclusion. Computer analysis saves time and energy, without compromising the accuracy of results obtained.
Reaction at Fy=42.66kN and Fx=65kN
Wind load acts at surface of the roof truss
Sunday, April 18, 2010
It is getting much challenging everytime...
The support of the roof truss
The member of the roof truss
The member section of the roof truss
The nodes of the roof truss
An overview of the roof truss
Friday, April 9, 2010
It was a long day
Thursday, April 8, 2010
Work… work…
By noon, Mr siva came to my room again to check on the progress of the analysis. At the same time, he reminded me that the representative from quantity surveyor firm wants the analysis as soon as possible. As soon as I realized the deadline was sooner than I thought. This time around I cannot afford to make any mistakes but to stay focus on the design. As a reason, mistakes requires correction and correction requires time. Due to insufficient experience in designing, correction is unavoidable. I have assigned a section of 76.0 x5.0 for top chord, however, it yields an error for plane flexural buckling and lateral torsional buckling. Therefore, larger section of 83.0 x 5.0 was required for the design.
I felt sense of accomplishment upon completing the design and analysis of roof truss.
The bending moment diagram of the roof truss
The shear force diagram of the roof truss
Wednesday, April 7, 2010
My first analysis
The deflected shapr of the continuous
Monday, April 5, 2010
On the first day
Doorway to my workplace
Upon arriving at office. Through my suprise I was no the only one joining the company for internship. Ronald from the same campus as i do will be joining the mechanical department for industrial training as well. Ms. Lyn from human resource department gave a brief introduction on the company;s organization, scope of work and background. After that, I was assigned a room to be stationed at. The moment i opened the door, the room was in all mess, documents and files were scattered all over the place as if before this it was occupied by an unorganized occupant. It took me quite a while to tidy and clean up the place.My room is in a mess
Now what is left undown is the computer. Idoubt it runs in such poor condition. It had a mouse and power cord missing. With the help of information technology (IT) technician, we manage to wake the computer from long sleep. Thereafter, the day ends earlier than I thought
My computer was in bad shape